PLN 8 million for the thermomodernization of Elk schools and Kindercrafts

23 May 2019, Author: Paweł Butwiłowski

City Ełk has gained more than PLN 8 million from THE EU for thermal renovation 4 and 2 City schools. Through funding The EU institutions will gain a new look and reduce the cost of their Maintain. The planned date of commencement of work is October 2019 The R.

Work will be coming soon in our city Associated with the Docieplan of the Elk Educational. Thermo 4 Elk Kindergartens and 2 city schools await you.

Thermomodernizacje will be carried out in the following buildings:

1.    Urban Kindergarten "Słoneczna Ósemka" at ul. Dobrzańskiego 3 in Ełku

2.    City Kindergarten "Not forgotten" at UL. The Slovakian 18 in Ełku

3.    Municipal Kindergarten "Światełko" at ul. Toruńska 8a in Ełku

4.    Urban Kindergarten "Mali Explorers" at ul. Kayki 8a In Ełku,

5.    Elementary School No. 9 at UL. Piwnika Ponurego 1 W Elk

6.    Primary School No. 3 at UL. Grodzieńska 1 in Elk.

See spot: Https://youtu.be/1Rhmcke5nl8

Building thermal renovation reduces the need for Heat and thus lowers its heating costs while simultaneously Improve thermal comfort. It can be comprehensive or focused on the aspect that influences the thermal performance of the building as much as possible.

In addition, the thermomodernization of the building Changes that will reduce heat escaping and ensure a more efficient and Economical and energy efficient interior heating, as well as usable water.

Scope of work Thermal insulation results from audits in individual buildings and includes:

Urban Kindergarten "Solar octal":

  • Warming Ventilated floor
  • Modernization Ventilation system consisting of the installation of hygrocontrolable ventilators Classical
  • Warming Ceiling above the Cellar
  • Exchange Old external windows
  • Exchange External-Output Doors
  • Warming Exterior walls
  • Warming Basement walls on the ground
  • Modernization C.O. System and D.H.W.

Urban Kindergarten "Forget":

  • Warming unventilated Strobe
  • Warming Exterior walls
  • Modernization Ventilation system consisting of the installation of hygrocontrolable ventilators Classical
  • Exchange External-Output Doors
  • Warming Basement walls on the ground
  • Modernization C.O. System and D.H.W.

Urban Kindergarten "Light":

  • Modernization Ventilation system consisting of the installation of hygrocontrolable ventilators Classical
  • Exchange External-Output Doors
  • Exchange Old external windows
  • Warming Basement walls on the ground
  • Warming Exterior walls
  • Warming Ventilated floor
  • Modernization C.O. System and D.H.W.

Urban Kindergarten "Mali Explorers":

  • Modernization Ventilation system consisting of the installation of hygrocontrolable ventilators Classical
  • Warming Exterior walls
  • Exchange External doors
  • Modernization C.O. System and D.H.W.
  • Exchange External windows
  • Warming Ventilated floor
  • Warming Exterior walls with mineral wool
  • Warming Basement walls on the ground

Primary School No. 9:

  • Exchange External windows
  • Warming Ventilated segment A, B, D
  • Warming C and E segment roof
  • Modernization C.O. system, D.H.W. and heat node
  • Warming Outer walls of the ground and ceiling above the crossing
  • Exchange External doors
  • Warming Basement walls on the ground
  • Modernization Kitchen ventilation

Primary School No. 3:

  • Exchange External doors
  • Exchange External windows
  • Warming Exterior walls
  • Warming The gym and its facilities
  • Warming Ventilation above the main building of the school, the liaison and the Room facilities
  • Warming Basement walls on the ground
  • Modernization System C.O.
  • Modernization Kitchen ventilation

Total investment Value is more than 11.8 million PLN. In this funding more than PLN 8 million from the EU.

Own contribution of the city of Ełku is more than 3.8 million PLN. The funds come from the regional operational programme Warmian-Masurian Voivodeship for the years 2014 – 2020.


Planned Start date The work is October 2019.

Works are to be completed in December 2020.