Kolejowa Street - on the section from Wilcza Street to Wczasowa Street - will be expanded. This week, the construction site will be handed over the project contractor. The work will begin before winter, but will take place outside the roadway's outline. This year, works will be carried out related to the construction and reconstruction of stormwater drainage.

The city obtained funding for the investment from Government Road Development Fund. The total value of the works carried out will amount to 4.1 million PLN, of which nearly 1.6 million is funding.

The entire scope of work includes:

  • Construction of the roadway structure (street width - 6 m),
  • construction of a
  • sidewalk from paving stones,
  • construction
  • and reconstruction of driveways from paving stones,
  • construction of pedestrian and bicycle paths with paved surfaces Construction
  • of a
  • telecommunication channel,
  • Construction and reconstruction of stormwater drainage networks,
  • Construction and reconstruction of water and sewage networks,
  • Construction and reconstruction of street lighting.

Road expansion work is expected to be completed by the 30th September 2027

 

Total investment value: 4,104,174 PLN (including cost reconstruction of the water and sewage installation covered by PWiK - 784,967 PLN)

Value of eligible costs: 3,170,850 PLN

Funding amount: 1,585,425 PLN

Source of funding: Government Road Development Fund