News

Author: Joanna Kowalewska | Publish date: 09 November 2022

Revitalization of Ełk courtyards

09 November 2022, Author: Joanna Kowalewska

Work is underway to revitalize the backyard area within Wojska Polskiego 35-39. As part of the work, m.in roads will be made access roads, parking and elements of small architecture.

The scope of the contract includes the revitalization of the area, including m.in.: construction of access roads and parking spaces. New ones will be laid sidewalks, installed park benches, trash cans and lighting of the area. There will also be a playground for children.

The cost of performing works on the basis of a contract with the contractor is 833 478,71 PLN The planned date of completion of the revitalization is the beginning of December 2022