News

Author: PSK/ ZI | Publish date: 09 May 2023

Another fragment of the bicycle path at 11 Street – go Listopada

09 May 2023, Author: PSK/ ZI

City Ełk signed a contract m.in for the construction of a bicycle path along 11-go Street November and reconstruction of public transport stops. This is the third contract under the project Improvement of urban mobility in MOF Ełk - line no. 2. The completion of works is planned for the end of October 2023.


Contract amount: 1 638 000 PLN

Scope of the project:

- construction of a bicycle path with bituminous surface along 11 street Listopada with a length of approx. 630 m from the roundabout of Dr. J. Rejewskiego to the intersection with ul. Polish Army;

- construction/reconstruction of pedestrian routes,

- purchase and installation of 2 new bus shelters with trash bins and bicycle racks: 11 Listopada Street (at the intersection with Tuwima Street), ul. Mickiewicza (at the intersection with Dąbrowskiego Street);

- construction of a new bus bay, purchase and installation of a bicycle repair station at the bus stop at 11 Listopada Street;

- purchase and installation of one bicycle shelter at the Water Park at ul. Pilsudski.

Expected Time of completion of works: end of October this year.

The implementation of the project will contribute to increasing the availability of services public, because the route of bus line No. 2 as well as bicycle paths along it, they lead to: School Complex No. 1, Ełk City Hall, Starosty District in Ełk, city stadium, Water Park and many others public facilities.

Project co-financed by the European Regional Development Fund in under the RPO of the Warmian-Masurian Voivodeship for the years 2014-2020 and the budget state.