The city has chosen the contractor of the works that will build the rainwater drainage system of the street Kraszewskiego in the Zatorze housing estate. The value of the works is PLN 498 thousand.

Was selected contractor for the rainwater drainage system on Kraszewskiego Street. As part of the work A drainage system with a length of approx. 232 m will be built.

In As part of the works, the surface of Kraszewskiego Street will be partially reconstructed with its inclusion in Tęczowa Street and replaced and supplemented unilaterally curb at a length of approx. 210 m.

At restoration of the surface of Kraszewskiego Street with the inclusion of Tęczowa Street milling will be carried out on the entire width of the existing pavement, and road troughing.

However The restoration of the new street surface will be carried out under a separate contract for the renovation of Kraszewskiego Street, which was concluded last year.

Value works: PLN 498,150.

Measures They come entirely from the city's budget.

Deadline implementation: 150 days from the date of signing the contract

 